A Utah kitchen remodel typically takes 6–12 weeks of construction, plus 3–8 weeks of design, selections and cabinet lead time. Refreshes can finish in 3–5 weeks, while structural or custom projects may take 4–6 months from first meeting to final walkthrough.
Typical timelines by project type
| Project | Design & ordering | On-site construction |
|---|---|---|
| Refresh / refacing | 2–4 weeks | 1–4 weeks |
| Mid-range remodel | 3–6 weeks | 5–8 weeks |
| Full gut remodel | 4–8 weeks | 8–12 weeks |
| Structural / open concept | 6–10 weeks | 10–14 weeks |
| Luxury custom | 8–14 weeks | 12–20 weeks |
What affects the schedule
- Cabinet lead times: 4–12 weeks depending on type.
- Permits and HOA review: days to a few weeks.
- Stone fabrication: typically 1–2 weeks after templating.
- Appliance delivery dates and special-order items.
- Winter weather can affect exterior work such as bump-outs.
Typical construction sequence
- Week 1: demolition and protection
- Weeks 2–3: framing, electrical, plumbing and inspections
- Weeks 3–4: insulation, drywall, texture and paint
- Weeks 4–6: cabinets, countertops, backsplash and flooring
- Weeks 6–8: lighting, appliances, punch list and final walkthrough
Figures are planning estimates based on typical Utah County projects in 2026 and are not a quote. Your price depends on your home, selections and scope.